A bill of materials with parts you can still source next year

A complete bill of materials with order numbers, alternatives, and lead times, so one missing chip cannot stop your first production batch.

Schedule a free intake

The prototype works. The circuit board is tested, the firmware does what it should, and the first client wants 20 units. Then you open the bill of materials and find that the microcontroller from the prototype has a 50-week lead time. The sensor has been discontinued by the manufacturer. And the connector came from a leftover lot at an online store that no longer carries it. We make sure your bill of materials is right before you order, not after.

Why a prototype BOM is not production-ready

A prototype uses what is available today. That works for one unit. A production batch multiplies every price, minimum order, and supply risk by 20, 100, or 1,000. A chip that is slightly too expensive, a capacitor only sold in lots of 5,000, a module the manufacturer drops next year: with one unit you do not notice, with a batch you do.

We review the schematic and bill of materials line by line. For every part, we check its lifecycle status at the manufacturer, how many suppliers carry it, the minimum order quantity, and the price at your volumes. Parts that are a risk on any of those points get flagged. Usually that is a handful on a list of a hundred, and exactly those few decide whether your batch ships on time.

A second source for every critical part

For every flagged part, we look for an alternative. Preferably one with the same package and the same pins, so the circuit board does not have to change. A resistor or capacitor is usually replaced in no time. A microcontroller or a radio module is a different matter. Then a small change to the design through PCB and electronics design is sometimes the better route, and we work that out for you before you choose.

The result is a bill of materials in which every critical part has a second source. If the first supplier quotes a 40-week lead time, the alternative is already on the list. You do not have to go looking for a substitute in the middle of production, and assembly does not have to stop until someone has found one.

Compare price, lead time, and risk

We collect prices and lead times from the major distributors and, where it pays, directly from the manufacturer. We compare them by part and by quantity, so you see what a batch of 50 costs and what happens if you order 200. Often a slightly more expensive part that ships now turns out cheaper than a cheaper one you wait three months for, because your batch is sold three months earlier.

Parts that are out of stock everywhere can sometimes still be found through brokers. That carries a risk of counterfeits, and we take it seriously. We verify the origin and test a sample on our automated test systems before you buy a whole lot. If the lot is bad, we tell you right away and keep looking.

From purchase order to the next batch

You decide how purchasing runs. If you prefer to order yourself, you get a bill of materials with manufacturer part numbers and order numbers per distributor, ready to import into the online store of your choice. If we handle small-batch manufacturing for you, we take care of purchasing and incoming inspection, and you see for every part where it came from and what it cost.

It does not stop there. We advise which parts to keep in stock for repairs and for the next batch, and which to order per batch. That keeps your money out of boxes of capacitors, and it keeps you from being unable to build a batch a year from now because one chip has disappeared. The bill of materials and the supplier data are yours, in a format you can use without us.

01, RESULT

A bill of materials with manufacturer and distributor order numbers
A second source or alternative for every critical part
Price and lead-time comparisons for your batch size
Warnings for discontinued and end-of-life parts
Inventory advice for repairs and the next batch

Process diagram

Process diagramProcess diagram: Prototype bill of materials → One chip with a 40-week lead time → Component selection and sourcing. Bottleneck: One chip with a 40-week lead time. Optimized: Batch built on schedule.MREVIEWPrototype bill ofmaterialsBOTTLENECKOne chip with a40-week lead timeComponent selectionand sourcingBatch built onscheduleProcess diagramProcess diagram: Prototype bill of materials → One chip with a 40-week lead time → Component selection and sourcing. Bottleneck: One chip with a 40-week lead time. Optimized: Batch built on schedule.MREVIEWPrototype bill of materialsBOTTLENECKOne chip with a 40-week leadtimeBatch built on scheduleComponent selection andsourcing

02, HOW WE WORK

  1. We review your schematic and bill of materials for scarce, discontinued, and single-source parts.

  2. We find a second source or a compatible alternative for each risky part.

  3. We compare prices and lead times from distributors and manufacturers at your quantities.

  4. You choose the balance between price, lead time, and risk, then buy directly or let us handle purchasing.

  5. We deliver the final bill of materials with order numbers, alternatives, and inventory advice for the next batch.

FAQ

FAQ

Can you source parts that are out of stock everywhere?

Sometimes, through brokers selling remaining inventory. Counterfeits are a risk, so we verify the source and test a sample before you buy a full lot. A substitute is often faster and safer. We coordinate any circuit-board impact with PCB and electronics design.

Do we have to purchase the parts through you?

No. You can order directly from the bill of materials we provide. We can also handle purchasing when we provide small-batch manufacturing and assembly. In either case, you see each part's source and cost.

What if a part becomes unavailable during production?

We use the approved alternative already listed in the bill of materials. That is why we find alternatives before a supplier quotes a 40-week lead time. If no replacement exists, we tell you immediately and assess a small design change.

Schedule a free intake.

Schedule a free intake

Open contact menu

Carlos Kroon Optimi

Good afternoon 👋

How can I help?

Mon–Fri, 9:00 AM–6:00 PM · We usually respond within one hour on business days.